Project Updates

Project Phasing

Project Phasing Board

Proposed Construction Activities

November 11, 2018

  • Phase 1D is tentatively scheduled to be complete November 21, weather dependent. Also note that the opening in the median on 156th at Fantasy’s driveway will be closed off prior to Phase 1D opening.

November 1, 2018

  • Finishing mainline paving on Phase 1D, backfilling curbs and working inlets and median surfacing
  • Begin Fantasy’s north driveway and sidewalks in Phase 1D
  • Continue noise wall #2 and begin grading for noise wall #1

October 26, 2018

  • Finishing mainline pours on west taper area of Phase 1D near 161st St., followed by sidewalk and driveway paving
  • Continuing with noise wall #2 on the north side of Harrison
  • Various clean up items such as fencing, sprinklers, seeding, etc.

October 1, 2018

  • Weather dependent, paving of westbound lanes on Phase 1D
  • Finish out driveways and sidewalks within Phase 1
  • Continue noise wall #2 (northeast) drilling for pilasters

September 19, 2018

  • Continue storm sewer installation, grading and paving prep in Phase 1D
  • Preparations for seeding of Phases 1A-1C
  • Preparations (including tree and fence removals) for noise wall #2 (northeast wall.)

August 20, 2018

  • Phase 1D removals including pavement and storm sewer
  • Begin new storm sewer installation in Phase 1D
  • Continue to finish sidewalks, walls and fences within Phase 1A, 1B and 1C
  • Finish traffic signal at 156th & Harrison St.
  • Utility relocations in Phase 1D

August 8, 2018

  • Phases 1A, 1B and 1C will be open to traffic Friday, August 10 by 3 pm
  • Phase 1D (west of 156th) will close at that time
  • Intersection will be stop controlled in all directions until the signal is operational

August 1, 2018

  • Finish median surfacing and temporary pavement in Phases 1A-C
  • Pour sidewalks on 156th St. and clean up prior to opening on Aug 10
  • Continue work on staining and temporary seeing along noise wall 3
  • Continue work on retaining walls, fences, etc.

July 16, 2018

  • Complete Phase 1A, 1B and 1C paving
  • Continue work on paving remaining driveways and sidewalks
  • Continue staining southeast noise walls
  • Install fences on retaining walls in Phase 1A

July 2, 2018

  • Pave 154th north, 156th south turn lanes, median surfacing
  • Driveways for CenturyLink, Fantasy’s and private drives
  • Construct fence on Wall B in front of storage facility

June 13, 2018

  • Rework subgrade due to rain, expect to pour remainder of 156th Phase 1B next week
  • Finish removals of 156th Phase 1C and begin laying storm sewer
  • Finish north leg of 154th St.

May 31, 2018

  • Paving westbound turn lanes on Harrison St.
  • Prep and pave 154th St north, driveways to Omaha Storage, Century Link and Fantasy’s
  • 156th St. north of Harrison will close Monday, June 4

May 16, 2018

  • Due to weather delays, paving of southbound lanes on 156th will occur towards the end of the week
  • Remove 156th & Harrison signal
  • Begin retaining wall B in front of Omaha Storage

May 3, 2018

  • Completing storm sewer work on south leg of 156th Street
  • Prepare subgrade of southbound 156th Street lanes in preparation for paving next week
  • Wrap up seeding and fence work behind south noise wall

April 23, 2018

  • Finish storm sewer pipe within Phase 1A
  • Continue retaining wall construction within Phase 1A
  • Close 156th Street, begin pavement removals in Phase 1B
  • Pending overhead power relocation, begin northeast noise wall grading

April 16, 2018

  • Finish junction box construction
  • Begin laying storm sewer pipe within phase 1A
  • Begin retaining walls B, C, and D
  • May begin tree removals pending bird surveys

April 9, 2018

  • Continue with removals for Phase 1A and storm sewer construction.
  • Grading and utility relocation work along northeast noise wall
  • Temperature dependent, seeding behind south noise wall
  • Construct retaining wall by Omaha Storage

April 2, 2018

  • Continue construction of box culvert extension and junction box
  • Grading and utility work to begin along northeast noise wall
  • Surface removal along south side of Phase 1A work area