Project Information

 

Harrison Street is an important corridor for southwest Omaha and Millard.  Improvements for this mile-long project include adding four lanes with raised medians, curbs and gutters, sidewalks, new traffic signals and noise walls.

Project Schematics

Harrison Street Cross Sections
Harrison Street Cross Sections

* click above image to open a larger version

Project Schedule

June 2014 : Project kick off; survey and field work begins
July 2014 : Engineering design begins
May 19, 2015 : Public Meeting to introduce the project
December 2016 : Right-of-way appraisals, negotiation, and acquisition.
August 2017 : Utility Relocations Begin
September 2017 : Design and right-of-way acquisition is substantially complete
September 2017 : Project is bid; contract awarded
October 30, 2017 : Public meeting to review construction phasing and final plans
November 6, 2017 : Estimated project construction start
March 22, 2018 : Public construction kick-off meeting for phase 1
April 2018 : Phase 1 construction begins
November 2018 : Phase 1 construction complete
March 2019 : Public construction kick-off meeting for phase 2 & 3
April 2019 Phase 2 and 3 construction begins
End of 2019 Construction of the entire project complete

 ** Please note: All future dates are estimates and subject to change